This multi-level building consists of 38 apartments and is located in the eastern suburbs of Melbourne. The building had both Aluminium Composite Panels (ACP) and expanded polystyrene.

Ninety percent of the ground floor apartments had significant water ingress with one apartment being unliveable for 6 years. This caused significant financial and emotional stress to the owner of the apartment who could not live in the property or tenant it out.

Water ingress is when external water is able to enter a building. This can result from poor construction, poor design, or the age of a building. Water ingress can create significant structural, non-structural and occupant health problems and must be addressed as soon as issues are identified to minimise the cost and scale of the remediation. Over time water ingress has a compounding effect in spreading through buildings and damaging its infrastructure.

Project Background

Description

PASG Projects Analysis and Scope of Project

ASG Projects met with the strata manager and the owners corporation-committee to present the PASG Projects process to complete a thorough review of the building to identify the extent of the water ingress.

Our detailed inspection process identified the following issues
  • Sliding windows installed incorrectly without end caps. This resulted in water entering the window frame and then pouring into the plaster cavity.
  • Window hobs were not fit for purpose and were crumbly.
  • No water membrane under any of the courtyard pavers or balcony tiles. Hence water was able to access the underlying structures.
  • The roof had overflow issues that allowed water to access the ceilings below.
  • Planter box membranes had not been installed allowing water to seep from the planter boxes.
  • The lower roof membranes had failed well before the end of their useful life.

A key consideration was understanding the extent of the frame rot due to the water ingress. A report was produced for the strata manager and owners corporation-committee.

PASG Projects Role

With the building assessment completed PASG Projects defined the scope of project and produced request for tender for contractors to price the remediate works. We assessed the tender submissions ensuring “apples with apples” and the scope had been included and made clarifications where necessary. We drafted the Contract and administered the Contract and administered the Contract as superintendent through the construction phase.

Click here to obtain a PDF copy of this case study.

Real people, lasting outcomes.

With our support, clients have secured properties, grown portfolios, and moved
closer to the lifestyle and goals they once thought were out of reach.

Barry Murphy - The OC Chairperson from Pemberton (NSW)

"Turning overwhelming challenges into real progress."

Matt & the team at PASG were exceptional. When a BWRO was issued on our building and the developer was liquidated, they broke down what seemed a monumental and overwhelming hurdle into simple smaller tasks, using common sense to tick of smaller items concurrent to preparing scopes for more significant items listed on the BWRO. It’s the first time we had seen real progress after spending lots of money on consultants and industry experts with no real gain. Well worth engaging these guys!!

Rafael Pentayitis

"Outstanding support. Exceptional outcomes."

PASG has provided outstanding support to a number of our clients. Their team has played an integral role in guiding the projects, maintaining clear and consistent communication, negotiating cost-effective outcomes, and ensuring all remediation work is completed to the highest standard. Their proactive and collaborative approach has made a significant impact, and we truly appreciate their commitment to delivering quality results.

Lachlan McGregor

"Complex projects, made seamless."

PASG turned a complex cladding replacement project into a seamless experience. Their advanced technology and clear communication ensured we understood every step, making our building safer and significantly improving its value. Highly recommend their professional team!

More case studies